March 19, 2007 - Screening of material for utility trenching.    
 
     
March 19, 2007 - Placement of on-site utilities within utility trenches.
 
     
March 19, 2007 - Connection to existing utility system.    
 
     
March 19, 2007 - Placement of existing utility pipe, backfill and bedding material in utility trench.
 
     
   
     
March 20, 2007 - Installation of on-site plumbing.    
 
     
 
     
March 20, 2007 -Pot-holing for existing utility locations on Russell Road.
 
     
March 20, 2007 -Pile of Type II.